| PPG 18 - ENFORCING PLANNING CONTROL - Dec 1991 | |
| HOME CUISINE ENVIRONMENT INSURANCE HORSES LEGENDS LAW NEWS PRODUCE RIGHTS SITE INDEX TRANSPORT WHISTLEBLOWING | |
| 
 Nelson says: "Are your council reasonable" 
 1.    New and substantially improved powers to
        enforce planning control are given to local planning authorities (LPAs)
        by the Planning and Compensation Act 1991. The enforcement provisions of
        the Act are based on the main recommendations of the report by Robert
        Carnwath QC, entitled "Enforcing Planning Control" (HMSO,
        February 1989).The report also recommended (Recommendation No. 14) that
        current Ministerial policy guidance about enforcement, in DOE/WO
        Circulars, should be revised, taking account of the concern expressed
        about certain aspects of the current guidance. This Note gives revised
        guidance. The
        New Enforcement Regime      2.     
        The new and
        improved enforcement powers provided by the 1991 Act are:-  1.     
        the power to
        serve a "planning contravention notice" where it appears that
        there may have been a breach of planning control and the LPA require
        information about activities on the land, or the nature of the
        recipient's interest in the land (new section 171C of the Town and
        Country Planning Act 1990); 2.     
        the power to
        serve a "breach of condition notice" where there is failure to
        comply with any condition or limitation imposed on a grant of planning
        permission (new section 187A of the 1990 Act); 3.     
        the ability to
        seek an injunction, in the High Court, or County Court, to restrain any
        actual or expected breach of planning control (new section 187B of the
        1990 Act); 4.     
        the power to
        serve a stop notice to prohibit the use of land as the site for a
        caravan occupied as a person's only or main residence, and to make a
        stop notice immediately effective where special reasons justify it
        (amended sections 183 and 184 of the 1990 Act); and 6.     
        improved powers
        of entry on to land for the LPA's authorised officer to obtain
        information required for enforcement purposes (new sections 196A, 196B
        and 196C of the 1990 Act). 7.     
        The penalty
        provisions for enforcement offences have also been revised. The maximum
        summary penalty on conviction of the offence of contravening the
        requirements of an effective enforcement notice, or the prohibition in a
        stop notice, is increased from £2,000 to £20,000. And, when sentencing
        a convicted person for an enforcement notice or stop notice offence, the
        Court is to have regard to any financial benefit which has accrued, or
        appears likely to accrue, to him in consequence of the offence .These
        exceptional summary maxima are intended to signal clearly how seriously
        Parliament regards this type of offence. The increased penalties are
        consistent with Government policy stated in the White Paper entitled
        "Crime, Justice and Protecting the Public" (Cm 965), published
        in February 1990. Chapter 5 of the White Paper acknowledges that there
        is increasing public concern about activities which damage the quality
        of people's lives (paragraph 5.8). It states - "If people ignore or
        flout laws and regulations designed to protect the public from serious
        harm, they should be properly punished, and the punishment should take
        account of the resulting profits or savings..." During consideration of the Bill in Parliament, amendments to impose
        a general duty on LPAs to ensure compliance with planning control were
        proposed. Although these amendments were not accepted (because the
        Government considers that enforcement action should remain within the
        LPA's discretion), the Government's view is that the integrity of the
        development control process depends on the LPA's readiness to take
        effective enforcement action when it is essential. Public acceptance of
        the development control process is quickly undermined if unauthorised
        development, which is unacceptable on planning merits, is allowed to
        proceed without any apparent attempt by the LPA to intervene before
        serious harm to amenity results from it. Enactment of the new and
        improved powers summarised in paragraph 2 gives LPAs a wider choice of
        available enforcement options. Authorities will therefore need to
        assess, in each case, which power (or mix of powers) is best suited to
        dealing with any particular expected, or actual, breach of control, to
        achieve a satisfactory, lasting and cost-effective remedy. Rapid
        initiation of enforcement action is usually vital to prevent a breach of
        control from becoming well established and more difficult to remedy. The
        General Approach to Enforcement     
        Nothing in this Note should be taken as condoning a wilful breach of
        planning law. LPAs have a general discretion to take enforcement action,
        when they regard it as expedient.They should be guided by the following
        considerations:-  1.     
        Parliament has
        given LPAs the primary responsibility for taking whatever enforcement
        action may be necessary, in the public interest, in their administrative
        area (the private citizen cannot initiate planning enforcement action); 2.     
        the Commissioner
        for Local Administration (the local ombudsman) has held, in a number of
        investigated cases, that there is "maladministration" if the
        authority fail to take effective enforcement action which was plainly
        necessary and has occasionally recommended a compensatory payment to the
        complainant for the consequent injustice; 3.     
        in considering
        any enforcement action, the decisive issue for the LPA should be whether
        the breach of control would unacceptably affect public amenity or the
        existing use of land and buildings meriting protection in the public
        interest; 4.     
        enforcement
        action should always be commensurate with the breach of planning control
        to which it relates (for example, it is usually inappropriate to take
        formal enforcement action against a trivial or technical breach of
        control which causes no harm to amenity in the locality of the site);
        and 
 Where
        Development is Carried Out Without Permission6.     
        In assessing the need for enforcement action, LPAs should bear in
        mind that it is not an offence to carry out development without first
        obtaining any planning permission required for it. New section 73A of
        the 1990 Act specifically provides that a grant of planning permission
        may relate to development carried out before the date of the
        application. Accordingly, where the LPA's assessment indicates it is
        likely that unconditional planning permission would be granted for
        development which has already taken place, the correct approach is to
        suggest to the person responsible for the development that he should at
        once submit a retrospective planning application (together with the
        appropriate application fee). It may also be appropriate to consider
        whether any other public authority (eg the highway or environmental
        health authority) is better able to take remedial action. 7.     
        While it is clearly unsatisfactory for anyone to carry out
        development without first obtaining the required planning permission, an
        enforcement notice should not normally be issued solely to "regularise"
        development which is acceptable on its planning merits, but for which
        permission has not been sought. In such circumstances, LPAs should
        consider using the new "planning contravention notice" to
        establish what has taken place on the land and persuade the owner or
        occupier to seek permission for it, if permission is required.The owner
        or occupier of the land can be told that, without a specific planning
        permission, he may be at a disadvantage if he subsequently wishes to
        dispose of his interest in the land and has no evidence of any
        permission having been granted for development comprising an important
        part of the valuation. As paragraph 14 of DOE Circular 2/87 (WO 5/87)
        points out, it will generally be regarded as "unreasonable"
        for the LPA to issue an enforcement notice, solely to remedy the absence
        of a valid planning permission, if it is concluded, on an enforcement
        appeal to the Secretary of State, that there is no significant planning
        objection to the breach of control alleged in the enforcement notice.
        Accordingly, LPAs who issue a notice in these circumstances will remain
        at risk of an award against them of the appellant's costs in the
        enforcement appeal. Where
        Unauthorised Development can be Made Acceptable by the Imposition of
        Conditions8.     
        A LPA may consider that development has been carried out without
        the requisite planning permission, but the development could be made
        acceptable by the imposition of planning conditions (for example, to
        control the hours, or mode, of operation; or to carry out a landscaping
        scheme). If so, the authority may invite the owner or occupier of the
        land to submit an application, and pay the appropriate application fee,
        voluntarily. It can be pointed out to the person concerned that the
        authority do not wish the business, or other activity, to cease; but
        they have a public duty to safeguard amenity by ensuring that
        development is carried out, or continued, within acceptable limits,
        having regard to local circumstances and the relevant planning policies.
        LPAs should bear in mind the need to consult on such applications in the
        normal way and the possible effect of such development on the functions
        of statutory undertakers. 9.     
        If, after a formal invitation to do so, the owner or occupier of
        the land refuses to submit a planning application in these
        circumstances, the LPA should consider whether to issue an enforcement
        notice. Section 173(4)(b) of the 1990 Act (as amended by the 1991 Act)
        provides that one of the purposes for which the LPA may, in an
        enforcement notice, require remedial steps to be taken is for
        "removing or alleviating any injury to amenity which has been
        caused by the breach". For that purpose, section 173(5) of the 1990
        Act provides that an enforcement notice may require, among other things,
        "the carrying out of any building or other operations"
        (paragraph (b)); or "any activity on the land not to be carried on
        except to the extent specified in the notice;" (paragraph (c)).
        Accordingly, where an owner or occupier of land refuses to submit a
        planning application which would enable the LPA to grant conditional
        planning permission, the authority would be justified in issuing an
        enforcement notice if, in their view, the unauthorised development has
        resulted in any injury to amenity, or damage to a statutorily designated
        site, which can only be satisfactorily removed or alleviated by imposing
        conditions on a grant of planning permission for the development. If an
        enforcement notice is issued to enable the LPA to grant conditional
        planning permission, they should explain clearly (in their statement of
        reasons for issuing the notice) what injury to amenity, or damage to the
        site, has been caused by the unauthorised development and how their
        conditional grant of permission will effectively remedy it.The owner or
        occupier will then have no doubt about the purpose of the enforcement
        action, or what he is required to do in order to remove or alleviate the
        perceived injury to amenity. Where
        the Unauthorised Development is Unacceptable on the Site but Relocation
        is Feasible10. 
        It is not the LPA's responsibility to seek out and suggest to the
        owner or occupier of land on which unauthorised development has taken
        place an alternative site, to which the activity might be satisfactorily
        relocated. But if, as part of their economic development functions, the
        authority are aware of a suitable alternative site, it will usually be
        helpful to suggest it, and to encourage removal of the unauthorised
        development to it. 11. 
        If an alternative site has been suggested, the LPA should make it
        clear to the owner or occupier of the site where unauthorised
        development has taken place that he is expected to relocate to the
        alternative site (or some other site he may prefer).The LPA should set a
        reasonable time-limit within which relocation should be completed. What
        is reasonable will depend on the particular circumstances, including the
        nature and extent of the unauthorised development; the time needed to
        negotiate for, and secure an interest in, the alternative site; and the
        need to avoid unacceptable disruption during the relocation process. If
        a timetable for relocation is ignored, it will usually be expedient for
        the LPA to issue an enforcement notice. In that event, the compliance
        period in the notice should specify what the LPA regard as a reasonable
        period to complete the relocation. Where
        the Unauthorised Development is Unacceptable and Relocation is not
        Feasible12. 
        Where, in the LPA's view, unacceptable unauthorised development
        has been carried out, and there is no realistic prospect of its being
        relocated to a more suitable site, the owner or occupier of the land
        should be informed that the authority are not prepared to allow the
        operation or activity to continue at its present level of activity, or
        (if this is the case) at all. If the development nevertheless provides
        valued local employment, the owner or occupier should be advised how
        long the LPA are prepared to allow before the operation or activity must
        stop, or be reduced to an acceptable level of intensity. If agreement
        can be reached between the operator and the LPA about the period to be
        allowed for the operation or activity to cease, or be reduced to an
        acceptable level, and the person concerned honours the agreement, formal
        enforcement action may be avoided. But LPAs should be aware of the
        possibility of intensification of the development after expiry of the
        statutory period for enforcement action. If no agreement can be reached,
        the issue of an enforcement notice will usually be justified, allowing a
        realistic compliance period for the unauthorised operation or activity
        to cease, or its scale to be acceptably reduced. Any difficulty with
        relocation will not normally be a sufficient reason for delaying formal
        enforcement action to remedy unacceptable unauthorised development. Where
        the Unauthorised Development is Unacceptable and Immediate Remedial
        Action is Required13. 
        Where, in the LPA's view, unauthorised development has been
        carried out and the LPA consider that -  1.     
        the breach of control took place in full knowledge that planning
        permission was needed (whether or not advice to this effect was given by
        the LPA to the person responsible); 2.     
        the person responsible for the breach will not submit a planning
        application for it (despite being advised to do so); and 3.     
        the breach is causing serious harm to public amenity in the
        neighbourhood of the site, the LPA should normally take vigorous enforcement action (including, if
        appropriate, the service of a stop notice) to remedy the breach
        urgently, or prevent further serious harm to public amenity. Unauthorised
        Development by Small Businesses or Self-Employed People14. 
        Although some breaches of control are clearly deliberate, the LPA
        may find that an owner or operator of a small business, or a
        self-employed person, has carried out unauthorised development in good
        faith, believing that no planning permission is needed for it. The cost
        of responding to enforcement action may represent a substantial
        financial burden on such a small business, or self-employed person. LPAs
        should consider this in deciding how to handle a particular case. 15. 
        The initial aim should be to explore - in discussion with the
        owner or operator - whether the business can be allowed to continue
        operating acceptably on the site at its current level of activity, or
        perhaps less intensively. The LPA should carefully explain the planning
        objections to the current operation of the business and, if it is
        practicable, suggest ways to overcome them. This may result in the grant
        of a mutually acceptable conditional planning permission, enabling the
        owner or operator to continue in business at the site without harm to
        local amenity. If the site's owner or occupier is at first reluctant to
        negotiate with the LPA, the service of a "planning contravention
        notice" may help to convey the LPA's determination not to allow the
        development to go ahead by default. 16. 
        If a mutually satisfactory compromise cannot be reached, and
        formal enforcement action is essential, the LPA should make their
        intentions clear, at the outset, to the owner or operator of a small
        business or a self-employed person. Unless it is urgently needed, formal
        enforcement action should not come as a "bolt from the blue"
        to a small business or self-employed person. It should be preceded by
        informal discussion about possible means of minimising harm to local
        amenity caused by the business activity; and, if formal action will
        clearly be needed, by discussion of the possible relocation of the
        business to another site. As explained in paragraph 10, it is not the
        LPA's responsibility to take the initiative in finding or providing a
        suitable alternative site. If formal enforcement action is likely to
        compel a small business or self-employed person to relocate their
        trading activities, the LPA should aim to agree on a timetable for
        relocation which will minimise disruption to the business and, if
        possible, avoid any permanent loss of employment as a result of the
        relocation. Once an enforcement notice has taken effect, LPAs should
        bear in mind that, where the circumstances justify it, new section 173A
        of the 1990 Act enables them to withdraw the notice; or to waive or
        relax any requirement in it, including the compliance period. A
        reasonable compliance period, or an extension of the initial period, may
        make the difference between enabling a small business or self-employed
        person to continue operating, or compelling them to cease trading. 17. 
        The Government remains committed to fostering business
        enterprise, provided that the necessary development can take place
        without unacceptable harm to local amenity. LPAs should bear this in
        mind when considering how best to deal with unauthorised development by
        small businesses. Nevertheless, effective enforcement action is likely
        to be the only appropriate remedy if the business activity is causing
        irreparable harm. Unauthorised Development by Private Householders 18. 
        When they are considering the possibility of enforcement action
        involving unauthorised development by a private householder, LPAs should
        bear in mind that independent professional advice about whether planning
        permission was needed for the development may sometimes not have been
        readily available, or affordable. This is particularly true where the
        householder may have relied on "permitted development" rights
        in the General Development Order (the GDO) as authorisation for the
        development, but a specified limitation has been exceeded in carrying it
        out. In these circumstances it is inappropriate to initiate a
        prosecution of a householder, under new section 187A(9) of the 1990 Act
        (prosecution for the offence of failure to secure compliance with the
        limitation imposed on a grant of planning permission by virtue of the
        GDO), unless the breach of condition notice served on the householder
        includes a full explanation of the allegedly unauthorised development
        and he has failed to take satisfactory steps to regularise it, despite
        being allowed adequate time to do so. In considering whether it is
        expedient to take enforcement action against development carried out in
        excess of the permission granted by the GDO, the LPA should have full
        regard to what would have been permitted if the development had been
        carried out in strict accordance with the relevant provisions. LPAs
        should not normally take enforcement action in order to remedy only a
        slight variation in excess of what would have been permitted by virtue
        of the GDO provisions. Enforcement
        of Planning Control Over Mineral Working19. 
        Minerals planning control is well established as part of the
        general planning system and there are no separate enforcement powers for
        unauthorised minerals working. The general policies and principles
        applicable to enforcement apply equally to minerals cases. Nevertheless,
        unauthorised minerals working sometimes poses particular enforcement
        problems, both in terms of the occasionally irremediable nature of the
        working and the speed at which damage can be caused. Certain of the new
        powers in the 1991 Act should therefore be helpful to mineral planning
        authorities (MPAs), to prevent damage which would otherwise be virtually
        or totally irremediable, either to the site itself or to its
        surroundings. 20. 
        It is clearly preferable for effective liaison and contacts
        between MPAs and minerals operators to be sufficiently good for
        contraventions of planning conditions to be avoided, and for any
        problems to be resolved through discussion and co-operation. In cases
        where formal enforcement proceedings are necessary, it is important to
        ensure that action is taken quickly. MPAs need to be able to stop an
        unauthorised activity as soon as it is detected. Examples are where a
        mineral operator is moving soil materials in contravention of clear
        planning conditions, so as to jeopardise the restoration and aftercare
        of the site; or where unauthorised excavation outside the permitted
        boundary causes irremediable damage, or endangers the safety and
        stability of the surrounding land. Section 183 of the 1990 Act (as
        amended by section 9 of the 1991 Act) enables a stop notice to be served
        at the same time as the copy of an enforcement notice; and section
        184(3) (as amended) now enables a stop notice to take effect before the
        expiry of 3 days, or immediately, where special reasons justify it - for
        example to prevent irremediable damage. The planning injunction
        provisions of section 187B are also available in respect of unauthorised
        minerals development. 21. 
        Further guidance on any more detailed aspects of enforcement of
        planning control over mineral working will be included, where necessary,
        in revisions to the relevant Minerals Planning Guidance Notes (MPGs). The
        Organisation of their Enforcement Functions by LPAs22. 
        How LPAs organise the administrative function of enforcing
        planning control is for each authority to decide. The organisation
        should correspond to the volume and complexity of enforcement casework
        in each LPA's area and be sufficiently flexible to adapt to short-term
        increases in the demand for enforcement. All authorities should ensure
        that there is a close and co-operative working relationship between the
        Planning Department and the Solicitor's (or Secretary's or Chief
        Executive's) Department. Without such an effective working relationship,
        formal enforcement action (which depends for its success upon speed of
        assessment and process) may be hampered by poor communications and
        misunderstandings. Public criticism is then likely, especially if
        statutory time-limits for taking enforcement action are allowed to
        expire because of administrative delay. Unless they have done so
        recently, all LPAs are recommended to carry out a thorough review of the
        effectiveness of their procedural arrangements for planning enforcement;
        and, where necessary, to introduce revised arrangements. 23. 
        When complaints about alleged breaches of planning control are
        received from parish or community councils, or members of the public,
        they should always be properly recorded and investigated. If the LPA
        decide to exercise their discretion not to take formal enforcement
        action, following a complaint, they should be prepared to explain their
        reasons to any organisation or person who has asked for an alleged
        breach of control to be investigated. Cancellation
        of Advice24. 
        The following PPGs are cancelled:-   PPG 1 (January 1988) - paragraphs 30 and 31;  PPG 4 (January 1988) - paragraph 19.  Paragraphs 15 and 16 of, and Annex B to, DOE Circular 22/80 (WO 40/80) are also cancelled. 
 THANK YOU MESSAGE 
 I would just like to say to the growing number of affected members of the public who telephone or email me, that I am so very pleased if anything we have published can be used to further just decision making. The encouragement is mutual! Lastly, if you cannot find what you are looking for on these pages and need some help, please help me to help others by emailing first. Please reserve the telephone for emergencies only. 
 | |
| 
 |